Clarification

This section provides guidance on how to conduct Post Tender Clarifications and Negotiation, where appropriate.

It is important that any discussions at this stage are fully documented.

Tender Clarifications

The objective at the clarification stage is to clarify the tenders as submitted.

Tender, or bid clarifications may become necessary during the evaluation of tenders. For example, where there are aspects of the bids that are unclear or contain minor errors.

You should consider whether an aspect of a bid seems ambiguous it might be prudent to request clarification.  


For example:

If the tender has asked for services to be completed daily and a tenderer responds that the services will be completed seven times per week, you should seek clarification that the services are indeed completed once per day.


Clarification may also be sought from tenderers on matters of quality performance or particular terms and conditions of contracts.

In seeking clarification, all communications with tenderers must be properly recorded so that an audit trail is maintained. If PCS-Tender is being utilised, clarifications  can be recorded on the system in the messaging area.

Negotiations in relation to price, essential aspects of the tender or other areas where bid improvements may be possible must not take place as part of the clarification process.

You should give all tenderers who meet the tender requirements the same opportunity to engage in tender/bid clarification. You must avoid unfairness or the impression of unfairness to tenderers.

Before awarding the contract you should ensure you receive the most up-to-date supporting documents referred to in the selection stage response e.g. certificates.

Post-Tender Negotiation (PTN), where it is practiced by an organisation, should be handled as a separate exercise from Tender Clarification.

Points to Consider

You should examine tenders to ensure tenderers:

  • are not making fradulent claims

  • have delivered similar types of work, if they have claimed to do so.

In doing so the following points should be considered:

Legitimacy

Are the claims made in the tender submissions legitimate and verifiable?

Scope

If tenderers are inexperienced in the type of work being tendered, tenders may appear excessively high or abnormally low. In both cases you should ensure that suppliers have understood the scope of the requirement

Interference

Have there been any perceived or obvious attempts to influence/interfere with the process?

Price discrepancies

Are there similar tenders with a large price discrepancy between different tenderers?  This could suggest collusion.  Are there tenders with large price discrepancies from tenderers who have worked in the same industry for some time? This could again suggest collusion.

Exclusions

Was anyone involved who should have been excluded as part of the selection process?

Conflict of Interest

Should a conflict of interest have been identified earlier in the process? Have conflict of interest declarations been examined and ratified?

Tone

Read and digest the tone of emails. Do they appear over friendly or allude to additional meetings either professionally or socially? Information is often exchanged during a visit or a social event: you should always maintain an audit trail of all correspondence

Submission

Were all tenders submitted on time and delivered in the prescribed manner? Examples of tenders being sent via a person within the tendering organisation could constitute a breach of protocol and should be examined

Late tenders

Were late tenders accepted and if so was there a legitimate reason?

Abnormally Low Tenders

Where tenders appear abnormally low for the offered supplies and services, you are required to clarify the price or costs proposed..

These clarifications may relate, in particular, to the following:

  • the cost of the manufacturing process of the services provided
  • the proposed technical solutions or any exceptionally favourable conditions available to the tenderer
  • the originality of the supplies or services proposed by the tenderer
  • the tenderer’s compliance with applicable obligations in environmental, social or labour law
  • the tenderer’s subcontracting arrangements
  • the possibility of the tenderer obtaining state aid

Note: if found that the tender is abnormally low due to an environmental, social or employment law obligation breach the tender MUST be rejected.

Where it is proven that an abnormally low tender is due to the bidder having receiving State Aid, the tender may only be rejected on that ground alone.  The rejection can occur only after consultation with the bidder: where they are unable to prove, within a sufficient time limit, that the aid is not compatible with the internal market.

Post Tender Negotiation

Post Tender Negotiation (PTN) should not be confused with 'tender' or 'bid clarification'.

Tender clarification is contact between the Procurement Officer and the tenderer(s) to clarify aspects of the tender which are ambiguous or irregular.

PTN may be used to refine and improve bid(s) from the preferred supplier(s) This is to ensure that prices, delivery or associated terms of the contract are competitive.  PTN is undertaken in open and restricted procedures as part of a competitive tendering process.

The potential areas for negotiation will differ for every contract but typical topics might be:

  • the terms of payment
  • quality of goods or services
  • supply and cost of spare parts
  • earlier delivery or completion dates
  • warranties and guarantees
  • documentation requirements
  • expediting and inspection procedures
  • maintenance and support
  • repair or after sales service
  • compensation for failure to meet specified requirements (e.g. of delivery, quality etc.)
  • Sustainable Procurement
  • possible Community Benefits
  • procedures for remedial action for unsatisfactory service

The list is not meant to be exhaustive.

Quickfire Guide

Quickfire Guide

Post Tender Negotiation

Before engaging in PTN, the following criteria must be met:

  • there must be a considered and soundly-based prospect of improving value for money
  • it must be in line with your internal governance and approval policies
  • trained and experienced purchasing staff must conduct negotiations
  • the negotiations must be fully documented, so that a clear audit trail is left

A clear "audit trail" must be available so that it can be seen that it was conducted in a fair manner.  The file should show:

  • the justification for PTN
  • the approval for PTN (at a suitably senior level of management)
  • the aim of the negotiation
  • the precise record of all exchanges, written and verbal
  • the approval for the award of contract

PTN must not:

Trade suppliers against each other

become any form of 'Dutch Auction': unfairly trading off one tenderer against another by using the lowest tender to seek a reduction in costs from the other tenderers

Distort competition

By allowing a tenderer, not clearly in the lead, a chance to improve its offer.

Create bias

Make changes which would result in a contract being awarded on terms more favourable to the tenderer

Adjust the specification

accept reduced prices but also adjust the specification in a manner more favourable to the tenderer. There is a risk that such an adjustment could have led to a different outcome in the competition even if the price was reduced commensurately

Be used automatically

Do not use on all procurements

 

When carried out in an atmosphere of openness and mutual trust negotiations can strengthen relationships with suppliers.

PTN must be a controlled and documented process.

The activities at this stage must be undertaken to  support the Principles of Procurement. As a minimum the processes must be carried out in a transparent way.  You must ensure equal treatment and no market place distortion.  You cannot favour or disadvantage a bidder.  It is your responsibility to ensure these requirements are met.

Consideration must also be given to Planning, Sustainable Procurement and Risk Management throughout this stage of the Procurement Journey.

Any documents you need are listed below

Negotiation Process

(file type: doc)